Feb. 16, 2020

PRN: Review static visual wireframes of Proun app and production timeline in person (Hito in NYC)

...
Mar. 15, 2020

PRN: Finish Testing/iterating Prouns–forms, general interaction, characterizations, etc.

...
Apr. 15, 2020

PRN: Finish tentative copy for App / interface (alerts, credits, info, etc.)
PRN: Finish Design of App/Interface
PRN: Finish Building App/Interface

...
May. 1, 2020

PRN: Finish reviewing and revising iterations of App on TestFlight–test UI, etc.

...
May. 15, 2020

PP: Edit and update App/Interface
PP: Write and finalize copy for 3D Text (French and English)
PP: Schedule time for French translators
PP: Complete 3D Text as 2D files
PP: Complete 3D Text as OBJs with LOD variants
PP: Tentative Placement of 3D text
PP: Review and revise iterations of App on TestFlight–test UI, etc.

...
Jun. 1, 2020

PRN: Review and finalize Copy for App / interface (alerts, credits, info, etc.)
PRN: Schedule time for French translators (if needed)

...
Jun. 4, 2020

PRN + PP: Write and Finalize Copy for App Store and Google Play
PRN + PP: Create Static Image Sets for App Store / Google Play
PRN + PP: Prepare App for submitting to App Store/ Google Play

...
Jun. 5, 2020

PRN + PP: Submit App to App Store and Google Play

...
Jun. 15, 2020

PRN + PP: Develop language and strategy for users to access downloads (Signage, pre-installed devices, etc.)

...
Jun. 19, 2020

PRN + PP: Install of elements
PRN + PP: Onsite testing/Revise placement of 3D texts
PRN + PP: Debugging
PRN + PP: Submit updates to App Store/google play

...
Jun. 24, 2020

Opening at Pompidou

...